In light of environmental and capacity challenges with their aging existing plant, in 2018 TasWater engaged Aquatec Maxcon to design and construct the new Longford STP – at the core of our design was Haskoning’s Nereda process. This was Aquatec Maxcon’s (and Australia’s) second Nereda Plant after the successful handover of Kingaroy STP selected through ECI.
With a combined catchment of the Longford township sewerage system as well as a neighbouring industrial wastewater catchment, the day one load to the new Longford STP was 2.5MLD (albeit a significantly stronger 2.5MLD than a regular sewerage catchment), and the design caters to the future catchment growth.
The full treatment process consists of:
The key design parameters were: